Today marked Patrick Nowakowski's first day as president of the Long Island Rail Road. Despite the fact that the new administration is now underway, there is still plenty of speculation about as to how the old one ended after the MTA suddenly announced Helena Williams' dismissal at the end of April. The MTA has not been open with their reasoning for removing Ms. Williams (beyond the scripted press release), and they many never show all of their cards, so we have to let speculation fill in the voids. I have my own suspicions as to the reason behind her dismissal, and many others have contributed their own.
Last night, Newsday contributed another story to the ring of speculation. According to this article, there is suspicion about that Helena Williams' opposition to the idea of Penn Station Access played a role in her dismissal. As you may or may not know, "Penn Station Access" is the idea of bringing Metro-North trains in from the New Haven Line and/or the Hudson Line into New York Penn Station on the west side of Manhattan. It has often been erroneously thought of as Metro-North's version of East Side Access, but Penn Station Access would use largely existing infrastructure, meaning the existing Hell Gate Line and Empire Connection and the existing New York Penn. This is nice, as it cuts down on costs substantially, but there's the unfortunate caveat that the existing New York Penn Station is very much in use, and there's little room left in the inn for Metro-North.
I have mixed feelings about Penn Station Access. I think it's a good idea, and I would like to see it happen at some point, but that point should be several years off. Much of my opposition to Penn Station Access, in a way, is not so much directed at the idea of the project itself, but rather the political cloud that surrounds it. The main champions for Penn Station Access have been Westchester County and Bronx politicians eager to please their constituients. And the primary opponents to Penn Station Access have been politicians from Long Island who are worried that their constituents will be slighted out of space in New York Penn Station.
Their concerns are not necessarily invalid. The problem with Penn Station Access is the fact that most people are going about looking at this the wrong way. They look at this as dots on the map. If the LIRR can add a dot onto their map it's only fair that Metro-North get to add a dot onto theirs. But it's tremendously more complex than that. Grand Central and Penn Station are far from similar--one is a station with more than forty platforms and more than 60 station tracks that is used exclusively by one and only one railroad, the other has just 11 platforms, 21 tracks, is shared by three different railroads that collectively operate close to 1,000 revenue trains on the average weekday in what could best be described as cramped quarters. Comparing Grand Central to Penn Station is like comparing LaGuardia Airport to MacArthur--and MacArthur would be the busier one.
And to add to this, the LIRR's East Side Access project is constructing an entirely new station at Grand Central deep below the existing one (like it or not, that's what they're going with). Therefore, bringing LIRR trains into Penn Station would result in no net loss of station tracks at Grand Central for Metro-North. Other than Madison Avenue Yard and the Lower Level Loop which was closed several years ago for ESA work, Metro-North has not been adversely affected by East Side Access.
Over at Penn Station, there is no plan to construct a new 8-track terminal below the exiting one (well, at least for Metro-North trains). The plan to bring Metro-North trains into Penn Station would involve no addition of capacity into the current station. Since they have no intention of adding capacity at Penn Station to support Metro-North trains, those slots are going to have to come from someplace else. I don't think Amtrak or NJTransit are going to volunteer some of their station slots for the sake of Metro-North commuters, so the last possible space to get slots is from the LIRR. And when East Side Access is completed, demand for the LIRR service to New York Penn will decrease slightly, and they will not need to run as many trains to Penn Station, so there will be some space opened up for Metro-North.
But a massive unknown in this equation is just how much space the LIRR might free up in Penn Station. It is all going to depend on how many people switch from Penn Station to Grand Central once East Side Access is completed. The more people that go to the East Side, the more room in Penn Station for Metro-North. But the less people that go to Grand Central, the less room for Metro-North.
So now it's just a manner of figuring out how many people are going to switch to Grand Central. But that's easier said than done. Studies have been done, and estimations of how many people might change to Grand Central, but even the most thorough studies mean nothing once the trains start rolling. In the end, I personally do not think that an extraordinary number of people will switch over to Grand Central. While Grand Central is in a new location on the east side, you have to think of what's around Grand Central and what's around Penn Station. Other than some office towers and the Lexington Avenue Line, there's not that much near Grand Central. There is far more near Penn Station in terms of tourist attractions, other connections, etc. (If the area near Grand Central was where everybody wants to be, why's Metro-North so eager to get to Penn Station?) I do not expect ridership at Grand Central to come anywhere close to what it will be at New York Penn, and I wouldn't put too much faith in the ridership projections put out thus far.
Ridership projections can be wrong--and I expect them to be. But that's not the end of the world. If they over-project the number of people that want to go to Grand Central, then they just scale back service slightly and slowly add it back as demand grows. But if they under-project the number of people who will want to remain at Penn Station after East Side Access is completed, then that is where we run into trouble. If the LIRR agrees to sign X amount of track slots in Penn Station over to Metro-North at some point based on these ridership projections, and these ridership projections come up wrong, will the LIRR be able to get those track slots back? I don't think there's a chance in the world.
If the LIRR loses these spots in Penn Station and then the ridership does not shift as planned, there is a slim chance of them getting those slots back, and the LIRR will be quickly back between a rock and a hard place (or rather, squeezed between a bunch of people standing in the vestibule of an M7). That is the big risk at play here.
This is one of the concerns that the Long Island politicians have--and their concerns are not unfounded. According to the Newsday article, Ms. Williams shared many of these concerns, and her disagreement with Prendergast and Cuomo (supporters of this project) might have contributed to her removal a week and a half ago.
Lots and lots of people have wondered why both sides have to be so against each other on this issue and and all the provincialism and territorial fiefdoms are what they are. Well, in a perfect world, we would be able to allocate enough track slots to give each of the four railroads as much as they need to sustain service into New York Penn Station. In a perfect world, the MTA would be able to give each of the different agencies enough money they need to fulfill what they need to do. But, alas, we live in an imperfect world. There is only so much room in Penn Station and there is only so much money in the MTA's budget, so there's not enough to go around. Everybody wants to have their cake and eat it too, but there's not enough cake to feed everybody.
Railroading has been an eternal game of who-was-here-first. At the end of the day, they are the LIRR's slots (it was their parent that constructed New York Penn Station over a hundred years ago), and their needs should get priority. An integrated and seamless regional rail network is much desired by some, but there are considerable obstacles, most of them financially-based, that few wish to consider. The politicians championing for this project now will be out of office by time this actually happens, so they don't give too hoots in hell as to how the details will get worked out down the line. It's good press now, so just tell me which camera I should look at.
If we wanted to sit down and come up with the money needed, things can be expanded and many of these obstacles can be resolved, but if everybody's going to have to fight for crumbs to do what's best for their agency, they're certainly going to fight for the crumbs.
It should be the agency presidents' jobs to look out for their agency, and do everything possible to make sure that their agency, and their agency's riders, are looked after. As fun as regional planning and the thought of a fully inter-connected regional rail network might be, that's not within the power of the MTA to accomplish that at this moment in time. And the motivation for that (i.e. financial motivation) will have to come from someplace beyond the MTA. All talk and no action (i.e. money) accomplishes nothing, it just makes everyone more angry and more antagonistic.
In my
opinion, what Ms. Williams lacked in railroad-operations knowledge she
made up with her background in Long Island-knowledge. She was at the MTA
for nearly 20 years at both Long Island Bus and the LIRR. She had an
an extensive background on the needs of Long Islanders that has been
unmatched by any other president in recent history. I do believe that she had Long Islanders best
interest at heart. An extensive background in rail operations is
certainly helpful, but if you don't understand the needs of the people
you are trying to serve, you are guaranteed to come up short. All things
considered, I think the railroad ran better with her in charge than it
did for decades prior. If this was the reason that Ms. Williams was dismissed (and I doubt it was), Long Island is a lot worse off than it was two weeks ago. I would rather have a president that is loyal to the 334,100 daily LIRR riders than a president that is loyal to one person at 347 Madison Avenue.
As to my thoughts on the progression of Penn Station Access at this point in time, I still firmly believe that there should be no further discussion on the actual Metro-North service with Penn Station Access until 7 to 10 years after East Side Access has opened. However, I would have no objection to beginning to ready the infrastructure required for Penn Station Access immediately. Lay the third rail, install the substation, and procure the necessary equipment, but make no promises or assurances or estimations as to any level of Metro-North services of any kind into New York Penn Station at this point in time.
Working to get the infrastructure needed in place now should be something they are working to do, as the redundancy will be good in the event of a catastrophic disruption*, but do it solely for the purposes of redundancy and resiliency, not for Penn Station Access.
(*-Note: I define the term "catastrophic disruption" as a serious failure of some piece of infrastructure that would result in severe delays for a substantial period of time. For example, a quarter mile stretch of the Park Avenue Viaduct collapsing into the street below one day would be considered a catastrophic disruption. For the sake of this discussion, I would not consider anything that had the potential of getting cleaned up in a week or two (i.e. the Spuyten Duyvil derailments, the Harlem Building explosion, the power failure on the New Haven Line) as catastrophic disruptions--sometimes you just draw the short straw, it happens to all of us).
Getting everything in place now will allow for one part of the region to not be crippled in the event of a catastrophic disruption, and allow for Penn Station Access to become possible, but when the time becomes appropriate.
Ideally, we get the infrastructure necessary for Penn Station Access in place now, and at the ribbon-cutting press conference for East Side Access--whenever that will be--the MTA can say that five years from this date they will evaluate the needs of both railroads at both terminals, they'll then work to develop a plan that will best accommodate everyone's needs and six and three-quarter years from this date they'll release that plan, and seven years from this date, service will start running and Penn Station Access will finally become reality.
Anything more accelerated than that will only spell disaster for the implementation of Penn Station Access. Rushing into anything too soon, or shedding any politically-motivated tears, in the meantime won't do all that much to help.
I don't agree with your estimation the popularity of GCT vs. NYPS. There is a heck of a lot more office space and tall officer buildings within walking distance of GCT than NYPS. LIRR wants ESA a lot more than MN wants NYPS.The Harlem Line will never access it. And some of that is merely to funnel MN's Wall Streeters down west side subways rather than the more over-crowded Lex.
ReplyDeleteBut I do agree with you assessment as to why Ms. Williams was dismissed. A synergy between her and LI politicians could out manuever East Bronx politicians who want NYPS access.
But other than going to the office buildings within walking distance of Grand Central, would there be any other reason for going there? If you work downtown it will still be faster to go to NYP or ATL and take the subway once you ride up the escalators at GCT and cram on the Lex. Yes, there's lots of people destined for the office space around GCT, but do they substantially outnumber the people going to the West Side, downtown, and through to New Jersey?
ReplyDeleteWould the lirr really not be able to get those slots back from mnr if they wanted to?
ReplyDeleteI do think East Siders outnumber West Siders. When MN passengers are polled, 70% prefer GCT over NYPS.
ReplyDeleteWall Streeters, who are declining in number as the area is going residential, will go whichever way their train is headed. For them, a LIRR zone express to Manhattan is still faster than a local to Brooklyn, regardless of what they do with that service, despite the IRT from Atlantic Avenue being 1 or 2 minutes shorter than it is from 34th. As for the Lex, peak load point is north of 42nd, and some do cram on the it to get to 51st and 59th. I'd also expect some of the 53rd Street Corridor/E train passengers from 34th to prefer GCT if headed to Lex/53rd.
New Jersey bound passengers, who are likely headed to Exchange Place, would take PATH from 33rd.
While the couplers became a non-issue by the tourist railroads and given AAR couplers, there were rumors around 2000 that they were thinking of rebuilding the C-1's to be the new Parlor car fleet. I think whoever started that didn't know about the MU jumper cable issue.
ReplyDeleteAmtrak's not there to mediate disputes between the two railroads. For all intents and purposes, they're the LIRR's slots, and if they want to willingly give them over to Metro-North, that's their decision. As long as the usage fees are rolling in, they don't care who's paying them, be it Metro-North or LIRR.
ReplyDeletePeople are also creatures of habit. I work two blocks away from GCT and I enjoy the walk over in the morning and evening. If I haven't retired by time ESA finishes, I probably would still stay going to Penn (that is unless they sent all of the trains to GCT)
ReplyDeleteLIRR's holds title to their slots, which is grandfathered back to PRR days, predating the MTA, and of course Amtrak, which didn't take ownership of the NEC until 1976. However, LIRR's de facto Board of Directors is the MTA Board, and they can sell LIRR's slots to MN for $1 a piece if they want to.
ReplyDeleteBased on everyone's comments, why was eight billion+ spent on ESA? Sounds like there would have been much better ways to spend the money. Based on the money spent, ESA should almost replace Penn Station access or at least have the same number of passengers.
ReplyDeleteEast Side Access and Penn Station Access are two completely different projects for two different railroads. The LIRR needed to add some sort of capacity sompleace in midtown Manhattan. They are maxed out at New York Penn Station and as demand grows, they will not be able to accommodate many more Manhattan-bound travelers, as a result they have to add some sort of capacity someplace. They could have added capacity to the existing Penn Station, but due to its layout, location, and configuration, that would have been extremely difficult (i.e. expensive) if not impossible, so the terminal would have to go someplace else. And, due to the sheer lack of land available in Manhattan, it would likely have to be a cavern, and at that point, it could be pretty much anywhere, so why not put it on the other side of Manhattan to give the people going to the East Side more options.
ReplyDeleteEast Side Access was primarily structured to be an alternate to New York Penn Station, taking some of the stress off that station (by people willing to go to East Side), thus allowing more room for expansion in New York Penn. It was never intended as a replacement for service to NYP, which I expect will be the dominant Manhattan terminal for some time.
Who all is so gung ho about taking Metro-North to Penn Station? As far as I can tell, Bronx politicians (and Cuomo, randomly) are really into adding more stations along the Hell Gate Line /future routing of the New Haven Line in the East Bronx. West Harlemites and Columbia University think the concept of a 125th Street MN stop using the Empire Connection is kinda cool, and there's little consensus on whether there should be a stop on the Upper West or where it should go. Proposing new stops on existing trackage is easy politics. People love the idea of a new fast train, even if they'd probably never take it 'cause the bus and subway are cheaper and you don't have to memorize a schedule and worry about missing them. Otherwise, it doesn't seem that tons of people are really jonesing to bring Metro-North trains into Penn Station. It's just the prospect of the new stops that's intriguing. But we do know that Long Islanders are scared and afraid. Is Penn Station Access going to even happen? It's a project with lots of detractors and not many champions. I predict they start building the stations in the Bronx with that pot of Sandy money ('cause... resilience!) but it takes more than a decade to finish 'em, and they give those trains terrible frequencies (like the local South Bronx stops on the Harlem Line, Melrose and Tremont), so maybe they need a track tops? LIRR doesn't even notice. What do they do with those New Haven Line "Train to the Game" Meadowlands specials? Same kind of deal.
ReplyDeleteDoesn't Penn have capacity off peak? If you have the infrastructure in place why not use it when you can, instead of only if there is a catastrophic disruption? I'm sure Westchester and Connecticut residents would appreciate a faster ride home after a Knicks or Rangers came for example.
ReplyDeleteNew York Penn is at capacity at all times and days at this point. On weekends, the schedules have to be configured in such a way that they can take one of each tunnel out of service at any point for trackwork, so Penn Station is not overflowing with capacity at any time. Midday weekdays and evenings are getting uncomfortably filled by its existing tenants as it is now too, with the Raritan trains squeaking in when possible, the LIRR bumping up service during the peak shoulder periods, etc.
ReplyDeleteIt's not impossible, but the number of Metro-North trains you'd might be able to squeak into the present NYP station, at any point during the day, can likely be counted on one hand. Then the question becomes is it worth it to go through the expense of qualifying crews--and keeping them qualified, having mismatched runs, long turns, etc. Most likely the answer is that it won't be worth it for the little space they will have until ESA is finished.
One question: How was NYNH&H access to Penn Station allocated in the Pennsy era?
ReplyDeleteAlthough I agree with Patrick that a conservative approach seems wise, I also think he's being overly pessimistic about demand among LIRR riders to end up at GCT. The concentration of office workers near Grand Central is significant on its own, but besides that it seems that people heading to just about any destination on the East Side -- whether for work or pleasure -- would prefer to connect to the Lex lines. (Patrick says "cram on the Lex" which seems to subtly imply that the cattle-car conditions will deter people, but let's be honest transferring at Penn during rush hour is no picnic either). Think of the East Side medical destinations. The museums and shopping.
ReplyDeleteThere's also a large midtown zone where destinations would be about equidistant from GCT and Penn, and presumably LIRR riders could choose either terminus based on the most convenient schedule. If I am bound for Times Square, there's not much reason to prefer one terminus over the other. You'd also obviously capture all the riders seeking to transfer to MNR, which I imagine would be similar to the number seeking NJT or Amtrak connections.
I'm not intimately familiar with the ridership studies that have been conducted, but is there good reason to think they're not pretty accurate? This seems like a fairly straightforward thing to quantify.
Anyway I agree that it would be unwise to irrevocably commit any LIRR slots at Penn to MNR until ESA is actually up and running, but I also see little reason to think there won't be a meaningful shift in riders to the East Side. And part of this, it seems, is up to the LIRR. If they choose to send fewer trains to Penn and shift those to GCT, the riders will follow. Riders who are clearly convenienced by going at GCT aren't the whole story. There's another class of rider who could just as easily end up at either place, and they'll move to GCT if the LIRR incentivizes them to do so by making Penn less accessible.
That "large Midtown zone" isn't that large. I made a map a few weeks ago using estimated transit times and Walkscore of all the different regions in the city where it would be faster to use one terminal over the other. While it may be the same distance from the street entrance of either terminal to that particular point, the travel times from Jamaica to NYP and GCT will not be the same (GCT is expected to be several minutes longer), and then once you take into account station access times (one is in a deep cavern, one is not), it does a considerable job of shifting that NYP/GCT dividing line over a lot. I'll post that map at some point.
ReplyDeleteI don't think there are any glaring issues with the ridership studies, but I'm taking ridership studies commissioned by the MTA for the purpose of justifying the construction of ESA with a grain of salt.
The idea of public transportation is to hopefully provide sufficient service to suit the needs of as many riders as possible, they should in no way be doing any "incentivizing." I see it every day since I use HPA/LIC. The LIRR has done a good job of incentivizing people of not using HPA/LIC by not providing much service to it. But that's a significant and inappropriate disservice to those who are best served by HPA/LIC.
If worst case projections about the North River Tunnels hold up it seems like NJT might be pushed out by Amtrak for lack of tunnel capacity. Then Metro North could run all the Hudson line trains they want to tracks 1-4.
ReplyDeletehttp://secondavenuesagas.com/2014/05/05/gateway-arc-sandy-and-the-ticking-clock/
That's not likely to happen, but if it did, tracks 1-4 would still not have third rail, so Metro-North or other Empire trains wouldn't be able to use those tracks. If they wanted to go through the expense of adding third rail to those four tracks (and a substation too, probably), they could, but the tracks are still stub-ended, so Metro-North would have to use two engines to operate onto those.
ReplyDeleteI too don't agree about demand for GCT. Anecdotal sure but a very large majority of passengers in my car every morning are headed straight to the E and alighting at 5th ave or Lex.
ReplyDelete