The May timetable change is upon us, as new schedules will go into effect on Monday, May 19, 2014. The new timetables bring back with them more service for the summer, as well as some other minor changes for summer trackwork programs. The schedules go into effect Monday and are effective through Labor Day, which is September 1st this year.
On the "Babylon Branch," one of two tracks will be out of service weekday evenings and late nights between AMITYVILLE and BABYLON for track surfacing. Local service is not affected, but some of the evening express trains that come from New York and connect to Patchogue or Speonk trains have fallen off the schedule for the summer, so those passengers will have to endure those brutal Babylon locals for a couple months! In total, 35 overnight Babylon trains and their connections have been adjusted between 15 minutes earlier and 13 minutes later to accommodate this work.
The Central Branch's single main track will be out of service weekday middays this summer for concrete tie work. The handful of midday Montauk Branch trains (3 eastbound and 1 westbound) will run via the Montauk Branch west of Babylon to facilitate this work (this results in one minute adjustments to running times).
Midday service on the Long Beach Branch still allows for single-tracking the entire branch, as the LIRR continues Hurricane Sandy recovery and resiliency work along the branch. Weekend service has been reconfigured on the Long Beach Branch to allow for single-tracking on weekends as well. This single-track outage on weekends during the summer will allow the LIRR to conduct switch replacements in VALLEY interlocking without disrupting service. The Long Beach weekend flyer, which departs Penn Station at 10:31am and runs non-stop to Long Beach on summer weekends, is also back this year, but it will depart about 20 minutes later than normal. The return trip (which runs express from Long Beach to Jamaica and them Penn Station) will run much like last year's. Because of these weekend adjustments, these trains' normal connections with the Montauk trains in Jamaica are broken, so the LIRR has added in several new dedicated weekend Freeport trains for Montauk travelers. The trains stop at Jamaica, where connecting passengers can transfer, then run express to Freeport where those going to Jones Beach can connect to bus service there.
All weekend westbound Mainline trains have had their running times shortened by about 1 minute or so now that the QUEENS concrete tie program has finished and service on all four Mainline tracks is restored. The concrete tie crews will be moving further east on the Mainline and will be installing concrete ties between Hicksville and Farmingdale midday weekdays. One of the two tracks will be out of service during this time, and trains 2317 and 2319 will be shifted 17 minutes later to accommodate this work.
Further east on the Mainline, weekend Greenport service is back full time for the summer (after being restored earlier this year), and train 252 is again extended to Greenport as train 254 on Summer Fridays this year, though I still wish they would have that train originate in Jamaica instead of sending it empty to Ronkonkoma on Friday afternoons!
On the Montauk Branch, all of the summer service (and confusing reference notes) are back again with this timetable change. Next Friday will be the first day that the onslaught of eastbounds will run, and Memorial day will be the first day for the westbound returns. Everything is essentially the same as it was last year--for better or for worse. The extra Montauk round-trip on weekends and the additional Speonk round-trip on weekdays that were introduced last year are also back again. Earlier in the year, train 2710's departure from New York Penn was shifted back one minute to 4:06pm, and that is kept for this year's iterations of 2710 (on Thursdays) and 2798 (on Fridays). The only real change in service for this summer is that train 2714 (the 5:09pm Penn Station to Speonk Dual Mode that is extended to Montauk) will also run on July 2 this year (the day before the day before Independence Day).
There are no notable changes to service on the Far Rockaway, Hempstead, or West Hempstead Branches. The Far Rockaway and Hempstead Branches stay "flipped" due to the Long Beach work, and the West Hempstead connections stay as they are now. Port Washington Branch riders see no real adjustments this time around.
In addition to these changes, there will also be a handful of additional non-revenue moves from New York and Jamaica out to places on Long Island to support ongoing work at West Side Yard and Johnson Avenue Yard. These changes will have no impact on other passenger trains.
One last note for Woodside travelers, the LIRR has put a special Woodside note on all of the timetables this time around stating that "Westbound trains may depart Woodside station up to three minutes earlier than times shown." This seems strange to me at first glance, because it doesn't appear like they've done any padding to times between Jamaica and Woodside and Woodside and New York, and westbound trains don't arrive at Woodside early too often, but we will see what becomes of this. Those of you who use Woodside for trains to New York, be aware!
PDF's of the new timetables are up now on the LIRR's All Timetables Page, and you can pickup paper copies in New York, Brooklyn, Jamaica, or a station near you.
[[Additionally, as a brief "programming note": I have a post about the Bay Shore Team Track that I meant to post yesterday, and some thoughts on through-running that I plan on posting tomorrow, but there's a huge pile of stuff sitting on my desk that has to get done first, but I'll try to get those up as soon as I can. Also, some of you have sent e-mails over the last couple days--they're in my inbox and I'll get replies out as soon as I can; thanks in advance for your patience!]]
Coming from Great Neck, it is not uncommon to be 2 or occasionally 3
ReplyDeleteminutes early to Woodside, especially on midday weekday trains which
have 10-11 minutes Flushing->Woodside instead of the more typical 7
minute (and occasional overnight 6-minute) running times. I suspect this
is to allow for single tracking for occasional midday work although it
has been in the permanent schedule for years.
I suspect rather than just saying westbound Port Washington branch
Woodside->Penn trains, it was just easier to apply it to all
Woodside->Penn, especiall since there are some trains with extra
running time over the standard 8 minutes Jamaica->Woodside as well,
like the westbound trains leaving Jamaica between 7 and 8am. Although I
can't see any of them ever being early to Woodside for a typical rush
hour, it could happen on a very quiet summer Friday or a "minor holiday"
when the LIRR runs a weekday schedule.
I think Midday and some weekend trains have some minor padding built in for stops at Mets-Willets Point during baseball season (and they just don't remove these times the rest of the year for the sake of consistency). Perhaps this is an effort to remedy that on non-event days.
ReplyDeleteWhat Greenport needs also is a Saturday morning express from Jamaica non-stop to Riverhead when equipment requirements are not so constrained. Montauk gets 4 such trains while Greenport gets just 1 useful Scoot. Lay-up the equipment on the pocket track in Greenport, and run back as a Sunday evening express. The Tour department should also take advantage of it for various North Fork Tours rather than all those damned buses from Westhampton or Central Islip in one direction or the other.
ReplyDeleteThen the dispatchers ought to attempt to send South Shore diesels via the Babylon Line when slots are available between locals. Threading those trains needlessly among all those Ronkonkoma, Huntington, and Oyster Bay trains is nuts. That would also save about 3 minutes per trip.
Train 2714 leaves Speonk later on Summer Fridays since the crews change in Speonk station for the trip east. The eastbound crew gets off at Speonk and a new crew gets on for the last leg of the trip to Montuak (much like two of the midday Montauk trains do). They have to do a break test and the like before setting off again, so they have to add a couple minutes to the schedule to ensure the train doesn't fall behind before venturing into dark territory.
ReplyDeleteWith just the existing equipment they can manage to do two additional trips on weekends. An eastbound train can leave Ronkonkoma at 7:35am (connecting with the 6:12am train from New York) run to Greenport, and deadhead back in time for the 10:35am run. Similarly, after the second and last westbound trip, the equipment could deadhead out to Greenport and run back at 9:11pm, arriving Ronkonkoma at 10:35pm, connecting to the 10:40pm train to New York, arriving there just before Midnight.
ReplyDeleteNot direct trains, but they wouldn't require any additional equipment.
Thanks Patrick. Of course - how forgetful of me - except for the final destination the times posted on the schedules are departure times, not arrival times. So a 5 minute addition to the Friday evening departure time of 2714 from Speonk would indeed be logical and necessary for a crew change and equipment checks. Westbound Train 2707 from Montauk, which I frequently ride, halts at the Speonk Yard where I observe a crew change that usually takes about 5 minutes.
ReplyDelete612am on a Saturday is pretty early for people to use. The subway system is still on 20 minute intervals. From a crewing standpoint, extending the Scoot's shift by 3 hours in the AM and 3 hours in the PM is probably a wash with simply running a 2 car express out from Jamaica around 8am, perhaps then pushing all the Scoots back an hour in the summer. Run it back Sunday around 4pm. There shouldn't be an equipment constraint for just 2 cars on a weekend, though I don't know how much they have to raid the Port Jeff and Oyster Bay yards to run the Sunday service back from Montauk.
ReplyDeleteThere are a considerable amount of people who get on that first AM Montauk train on summer weekends (and that connection leaves Penn as early as 6:30am or something like that), so I wouldn't underestimate the amount of people who might like to get out east sometime earlier than 1:11pm.
ReplyDelete