Saying that Long Island needs a third Mainline track in the worst way is understating it big-time. The LIRR's Mainline is absolutely at, or very, very close to, capacity during rush hours, and its current two-track, at-grade configuration makes it very prone to service disruptions. The way the mainline is currently loaded up during rush hours, if trains aren't run as close to the schedule as possible, the entire Mainline--and the entire railroad--can be affected. Just one late train during rush hours can delay as many as a dozen others. If something more severe happens, where one or both tracks on the mainline are knocked out entirely, forty thousand commuters from fifty-seven different LIRR stations see severe delays, and everyone else on the railroad gets effected consequently as well. Because the LIRR is wound so tightly at rush hour, if any one segment goes down, the entire railroad suffers. It's a problem unique to the LIRR because of how operationally complex it is--a disabled train on Metro-North's Hudson Line would never really effect trains on the New Haven Line to a considerable degree, but for some reason, one broken rail or disabled switch along the Mainline and the entire rush hour is shot.
And, as if on cue, the morning after this report came out, we had a rough morning rush on the Mainline. Train 2401 broke down in New Hyde Park, where the passengers were unloaded, and ended up limping to Jamaica, getting there almost an hour late. A train becoming disabled at that point in the rush hour (around 7:00am) would normally wreak havoc on the mainline in terms of congestion. "Luckily" there was also a broken rail in Bethpage later on in the rush that "saved" the riders from Port Jefferson, Huntington, Hicksville, and points west form bad congestion at the expense of even more delays for riders from Ronkonkoma and Farmingdale. There was still significant congestion at points, but it was less then it would have been had the problem at Bethpage not develop.
And there have been hundreds of service disruptions in recent history that could have had much less of an impact had there been a third track. Taking a cursory glance through 2013's OTP by day information, which has a list of major incidents that caused delays to 10 or more trains, I counted as many as 28 different disruptions that could have disrupted far fewer trains had there been a third mainline track. In particular, these five examples stand out:
- On 1/24/13, a broken rail east of Mineola caused delays or cancellations to 64 trains. Had a third track been in place, two tracks could have been maintained through the affected area (and three tracks in unaffected areas) and the impact on service would have been significantly less.
- On 3/26/13, another broken rail at NASSAU interlocking disrupted 110 trains. This could have been worked around had there been a third track, and while there still would have been delays, the impact of the broken rail would have been far less.
- On 11/20/13 train 603 became disabled at Carle Place at the onset of the morning rush hour. The train sat there for practically the entire rush hour, and a total of 76 trains suffered delays or cancellations as a result of only one track being available from NASSAU 3 to DIVIDE 1.
- On 12/6/13, a triple-header of disruptions caused a rough evening rush hour for Mainline riders. Between a motor vehicle striking a bridge at Post Avenue, a passenger on train 2061 needing medical assistance at New Hyde Park, and a vehicle stuck on the tracks at the New Hyde Park Road crossing, a total of 45 trains were delayed due to incidents that could have been much less disrupted if this third track was in place.
A substantial lessening of service disruptions on the mainline is just one of the benefits that a Third Mainline Track could bring. A substantial increase in reliability would not only improve on-time performance and reliability for passengers, but also cut down on the operational impacts that service disruptions have, like late turns of equipments or more penalty payments or overtime for train crews, all which add a lot to the cost of running the railroad.
Furthermore, the Third Mainline Track would not only reduce the ill-effects of constrained capacity on the Mainline, it would also provide for many more opportunities for service enhancements, both in the peak and reverse-peak markets. Some of the projects that the LIRR currently has planned, like the Ronkonkoma Branch Double Track project, would also potentially not be able to live up to their full potential should the Mainline Third Track not be built.
These are all just the operational benefits a third Mainline track could bring. I haven't even begin to delve into the economic and fiscal impacts that the third track can bring, which was the primary focus of the Rauch Foundation's report.
According to the report, just 9.8 miles of additional track can bring:
- 14,000 more jobs to Long Island
- $3 billion more in personal income
- An additional $5.6 billion towards Long Island's Gross Regional Product
- 35,400 new residents to Long Island
- $40 million in additional sales tack revenue
- $103 million in additional property tax revenue
"Job growth on Long Island has been sluggish for two decades, and a primary obstacle to growth is the lack of capacity for reverse-commuting on the Long Island Rail Road. Regular commuting (into New York City in the morning and back home in the evening) has been a major economic driver on Long Island for generations, contributing $26 Billion in personal income to Long Island’s economy in 2011 alone. Reverse-commuting (as well as regular commuting), however, is expanding the economic opportunities for Northern New Jersey, Westchester, and Southern Connecticut, but not Long Island. That’s in part why a separate report by the Long Island Index recently revealed that Long Island has only 195,000 square feet of retail space under construction, compared to 3,765,000 sq. ft. in Northern New Jersey and 1,980,000 sq. ft. in Westchester/Southern Connecticut."The report calls attention to the lack of revers-peak commuting capacity and how it is stifling economic growth on Long Island. The report indicates that the absence of reliable reverse-peak train service to Long Island during peak commute times greatly reduces the feasibility of reverse commuting to Long Island. The gap in service prevents many New York metro area workers who rely on transit from working on Long Island, even though their skills may be well-aligned with the needs of Long Island businesses.
The report highlights other areas in the New York Metropolitan area that have seen significant growth as railroads have made investments to improve reverse-peak travel. The report contrasted White Plains along Metro-North's Harlem Line and Hicksville along the LIRR's Mainline. Both are about 30 miles from Manhattan, but the deficit in service is substantial, and as a result, that has stifled economic development in the Hicksville area:
As a part of the study, Parsons Brinckerhoff constructed three scenarios using the New York Metropolitan Transportation Council's Best Practices Model to measure the future performance of the regional transportation network with and without Third Track:
2010 Service
•Based on NYMTC 2010 Build Scenario
2035 No-Build Scenario
•Based on NYMTC 2035 Build Scenario
•Includes East Side Access, Ronkonkoma Double Track, Second Avenue Subway, and the 7 Train
Extension 2035 Third Track Scenario
•Based on NYMTC 2035 Build Scenario
•Includes East Side Access, Ronkonkoma Double Track, Second Avenue Subway, and the 7 Train Extension
•Includes 17 additional AM trains enabled by Third Track
The report indicates that a third track on the Mainline would significantly increase eastbound (reverse-commute) train frequencies at Main Line stations during the peak period of 6-10am. Reverse peak gaps of an hour or more could be shrunk to around 20 minutes to almost every station, and about 10 minutes to Hicksville and Mineola.
The briefing book gives many of the details about the three different scenarios, but much of the details focused on the potential growth that could come as the direct result of more reverse-peak service, plus even more amplification of that growth due to as many as 10 potential transit-oriented developments:
The stark contrast between the numbers if a third track was built and if it was not is definitely noticeable:
It is clear that the lack of a third Mainline track severely harms Long Islanders both in the short-term, with less service and more disruptions due to constrained capacity, and in the long-term, by severely limited economic growth. An investment in the third mainline track cold pay itself off seven times over by 2030.
A third track should in no way be optional for Long Island--the benefits of the investment are clear, and the downsides of not building the third track are just as evident. Unfortunately, the report does not pay any attention to the local NIMBYs along the right of way that are single-highhandedly stifling all of this economic growth and service enhancements on Long Island, and how they should be dealt with. The LIRR should not let these NIMBYs hold this project up for one more second; it's probably one of the most, if not the most, critical project that the LIRR will need completed before East Side Access opens, and the fact that they're not even talking about starting it is very concerning. In all of the talk about East Side Access readiness, the Third Mainline Track is absent almost 100% of the time. This project isn't something that would be "nice to have" if the funding became available, it's a project that should have been started 10 years ago. There are lots of projects that are seemingly "indefinitely delayed" on the LIRR, but this is the most badly needed one of them all.
The LIRR needs to begin to crack down on these NIMBYs immediately. Over the last couple decades or so, things have begun to get out of hand--they bend to easily and avoid firmly standing their ground. Have the public hearings, let the NIMBYs complain, and then just built the thing. It's time we started laying some track and expanding some yards. As much as it stinks for those standing in the paths, to hell with the locals.