New posts will probably continue to be hit or miss for the next week or so as I'm in and out of town (accumulating Amtrak Guest Rewards points at others' expense). For the meantime, the MTA uploaded a series of pictures showing the latest progress of the East Side Access project. There are quite a few pictures (as well as a smaller set taken on June 3rd).
You can view the full set of photos on the
MTA's Flickr Stream, many of the photos in this set are exceptional. I have included below some of the highlights from the set, as well as some brief captions of what's going on in the photo. You might also find it helpful to check out February's
A Closer Look at East Side Access post, which brakes down each of the individual segments that are part of the project. All photos are credit: MTA Capital Construction/
Rehema Trimiew.
 |
| This photo shows one of the two giant station caverns. This cavern will feature space for four different 12-car trains, two station platforms, and a middle mezzanine between the two levels. There is a second cavern just like this to the left of this one in the photo. |
 |
| Supplies that will eventually be used in the finishing of this station cavern. |
 |
| Looking down at one of the two station caverns deep under Grand Central. |
 |
| Photo showing the opening where two different sets of tracks converge into one tunnel. |
 |
| Photo of one of the tunnels bored to connect the new station caverns to the western portal of the 63rd Street Tunnels in Manhattan. |
 |
| An opening in the tunnel where a two tracks meet and crossover can be placed to allow trains to go from one track to the other. |
 |
| A train of special construction equipment running on temporary tracks in the tunnels under Manhattan. |
 |
| Looking out from a tunnel portal into one of the two giant station caverns. |
The above pictures showed progress in the caverns and tunnels deep under Grand Central Terminal. The photos immediately below show a bit of the progress closer to the surface on the site of the future LIRR Concourse on the lower level of Grand Central:
 |
| Workers clearing space on the lower level of Grand Central (likely on the site of the former Madison Yard) for the future LIRR Concourse on the lower level. |
 |
| Debris being loaded onto a railcar for removal by Metro-North. |
The following set of photos were taken on June 3rd. They show some scenes of work being done in the station caverns under Grand Central. Note how some of the huge pieces of construction equipment look tiny in the huge station cavern. These photos are credit Metropolitan Transportation Authority/Patrick Cashin:
 |
| LIRR Workers preparing to pour concrete in one of the two station caverns at Grand Central. |
 |
| The four tunnel portals that head north/east towards the 63rd Street Tunnels and Queens. These four, along with four more tracks from the adjacent cavern, will converge to form the two track line to Queens. |
 |
| Crews using a crane to lift rebar. |
 |
| A number of people working to prepare one of the station caverns for concrete pouring. |
 |
| A crane that appears tiny in comparison to the massive station cavern. |
 |
| Crews working to pour concrete in the lower level of Grand Central. |
 |
| Concrete being poured in one of the two station caverns in Grand Central. |
 |
| One final photo of workers pouring concrete on June 3rd deep under Grand Central. |
While we are still quite a ways away from seeing the first train running into Grand Central, but work is visibly progressing--slowly but surely. Check back through some of the previous East Side Access photo updates (
November 2013,
June 2013, and
February 2013) to check out the progress that has been made just in the last year and a half or so. It's a major project, and hopefully one that will get back on the right track for completion in the reasonably near future.
Those caverns were all dug out of solid ground?
ReplyDeleteIf so, that's a metric buttload of dirt to have to shift. What on earth did they do with it? Haul it out by the trainload? And where'd they put it?
It's actually roughly 73.8 million metric tons of dirt. As of last February, MTA Capital Construction had removed roughly 40.5 million cubic feet of muck. That's about 75,000 truckloads of much, which, if lined from end to end
ReplyDeletewould stretch for over 700 miles (roughly the distance from New York to
Indianapolis). If all the muck was piled on a football field, it would
pile up to a height of 700 feet tall.
Most of the larger stuff is broken apart, sent in in pieces, then reassembled once they get to the caverns. The tunnels themselves are no taller than an M1.
ReplyDeleteHere's a stupid ESA question...
ReplyDeleteIf the clearances in the old tunnel are so small, and that new cavern has to be so deep, why didn't they just build new tunnels shallower and further north to use a few of the existing 40+ tracks at GCT? The east river tunnels were finished in 5 years a century ago. Maybe I'm monday morning Quarterbacking here, but it seems as though that route would have been a bit less ambitious, maybe they could have finished it in just 10 years ( assuming modern regulations and lack of planning accounts for a 50% reduction in productivity) , and run whatever equipment pleases them to boot.
I noticed on the ESA timetable posts that Jamaica to Grand Central is 5 minutes longer than Jamaica to Penn. Is that correct? Why so much more time? Where did that info come from? Thanks :)
ReplyDeleteHarold to NYPS isa pretty straight shot, mostly at 60MPH.
ReplyDeleteTo get to GCT, you go northwest to 63rd, then hang a 90 degree left turn in Manhattan and head south a mile.
As for being a time-saver for some, it is a bit oversold. Nothing can beat 17 minute ride to Hunterspoint, a 2 minute transfer on 6 flights of stairs to the #7,and a 5 minute ride to GCT. Better for Heart Health too.
I used Google Maps to measure the distance and Penn is actually .3 miles farther from Jamaica (via 33rd) than GCT (via 63rd/Park), so I guess you lose the 6 minutes in the curve from 63rd to Park? That seems extreme. ESA is using all new signals and track so you'd think you'd get some slight time savings from that too. If you add in the time it takes to get to the surface from ESA, it's about 11 minutes slower than going straight to Penn. Does anyone know where in the EIS or MTA website this scheduling info can be found??
ReplyDeleteIt's what you do in those last miles west of Harold.
ReplyDeleteTrains go pretty fast until about midway across Manhattan.
OTOH, a 63rd Street train would start slowing for the curve before they hit the Manhattan bulkhead, crawl around the curve, then never get a chance to resume speed since once the rear car of a 12 car train clears the curve, the front car is around 56th Street, at which point, they have to go slow for switches and splitting between the 2 caverns.
The scheduling info can't be found on MTA's website. This was a project of Patrick's he did himself.
ReplyDeleteBuilding a tunnel further north would make diverging from the mainline much more complicated.
ReplyDeleteThe decision to go with a deep-level cavern station over bringing LIRR trains into the existing station has been a heavily debated one. Ultimately, there were a number of disadvantages with bringing LIRR trains into the current GCT lower level (particularly, concerns over crowding on GCT's lower level, a significant grade up from the 63rd Street Tunnels, differing cab signal and third rail systems, etc.). The under-water tunnels are among the most difficult parts of the projects, and the fact that they were essentially finished before constructed started made things much easier. It would be very difficult in the 21st Century New York to get any under-water tunnel that was shallower than the one that is there now. The powers at be have essentially forbidden floating tunnel sections and sinking them into place in the river. All tunnels must now be bored under the water. You would have to go much further north, and the grades would be even more substantial, plus it would make diverging from the Mainline in Queens a lot more complex, like @Tug Thumper said. That would all add significantly to travel times, and reduce the anticipated benefit of ESA.
ReplyDeleteI did the math at one point, comparing grades, curve radii, likely switch speeds, and distance in the newly constructed portions of railroad, and the fact that GCT will be operated as a terminal station, so trains have slower approach speeds and less favorable signals then they would if they were in a through-station like New York Penn and came to the conclusion that Grand Central would be approximately 19 minutes past Woodside, or about 27 minutes from Jamaica (NYP is 20 minutes, HPA is 16 minutes). Add into that the time it takes to get from the cavern up to the street level, and it's not an incredible time savings.
ReplyDeleteI'm having a little trouble with the scale of things in those photos, especially the tunnels (4th through 7th). Either those tunnels are bigger than they look, or the rails are narrow gauge. Which is it?
ReplyDeleteI suspect I'm one of the few people that would argue that ESA is a waste of money, but primarily because the design is terrible. No European railway operator would build a giant eight track cavern for 24 trains per hour. Munich can achieve 30 trains per hour with a two track tunnel in the core that doesn't operate as a terminal. Even if we're not going to build a loop to downtown to connect with Flatbush, at minimum, we should force the LIRR to operate far more efficiently and with more rapid transit like practices as their European counterparts so we're not forced to pay more for an over-engineered station.
ReplyDeleteIf an 8 track cavern is too much money, what does tunneling instead a 2 track line from 42nd Street to Atlantic & Flatbush cost ? Then what do you do with all the trains ? Store in VD Yard ?
ReplyDeleteHowever, the TA does turn 28 #7 trains per hour at Times Square, a 2-track stub. The crews falls back 1 or 2 trains to give the T/O time to walk back 11 cars. However, they do not each have 1,200 people on board by the time they reach there. There are also FRA-mandated safety and brake tests, which take a few minutes. From there, I do not know the answer.