For many years, VD Yard looked much like this:
| Diagram of VD Yard, as it existed before the construction of the Barclays Center. (Diagram credit: Atlantic Yards FEIS) |
![]() |
| VD Yard in Brooklyn, as it exists today. (Photo credit: Benjamin Warfield) |
When all said and done, the "new" VD Yard would look something along the lines of this:
| (Diagram credit: Atlantic Yards FEIS) |
![]() |
| Photo showing the "temporary", unfinished VD Yard. (Photo credit: Benjamin Warfield) |
The reconfiguration of VD Yard was supposed to start and finish fairly early on in the Barclays Center project to minimize the effect on the LIRR, but it has yet to happen. And here we are, just a short while from the Barclay's center second anniversary, and the West Portal has still not been built. The project is only partially complete--the yard tracks themselves have been relocated to the east side of that three block box, and the drill track is in, but the last, and most important piece of the puzzle, the West Portal, has yet to be put in place.
As a result, trains have been on the eastern side of that three block box, but the only way out of the yard is still out the lead track at the eastern end of the yard. As a result, trains that want to go from the yard tracks to the station now have to pull out onto the drill track, reverse directions, travel over the lead track and into the tunnels, reverse directions again, and then head into the station. So, in essence, the reconfiguration--in its current state--has not removed the one reverse move that all trains previously had to make, it now added another one for trains coming from the bulk of the yard tracks, making using the yard even more inconvenient than it was before.
VD Yard has sat in its broken up, ruinous state for the past several years as construction on the Barclays Center continued and finished, however, chatter about VD Yard and the West Portal has been picking up again recently, as it has been reported that construction on VD Yard's West Portal, which would result in some lane closures on nearby roadways as a result, would begin sometime in the not too distant future, so there is hope that VD Yard might be getting its previously promised West Portal after all. Additionally, the MTA is asking the MTA Board Finance Committee later today to approve an amendment to the Atlantic Yards agreement between the MTA and Forest City Ratner. Part of the master plan for the Atlantic Yards site would involve decking over the new, permanent yard at some point in the future, and part of this amendment would permit the developer to begin constructing the platform over the remaining portions of the yard early--before the entire permanent yard is completed. Additionally, the agreement would take the MTA's due date of June 2016 for the permanent yard and push it back to December 1, 2017, giving the developer more time to meddle with the yard. The MTA is considering this acceleration a good idea, considering that it would allow the developer to get a good bit of the dirty work regarding the remaining deck and the permanent yard out of the way while the yard still isn't used much.
It seems as though VD Yard is not out of the woods yet, and it will still be mangled and tossed around for a little while longer as the developer scrambles to get everything in place, but there's still a decent chance that things will all end up the way they are supposed to in the end (albeit very delayed).
At the current moment, the LIRR doesn't have a significant interest in its service to Brooklyn, so having VD Yard in limbo for a short while longer is not the end of the world, but what the Atlantic Yards developers have done to VD Yard should be kept in the back of everyone's minds as future decking opportunities come up. The LIRR cannot really afford to let the Hudson Yards developers ruin West Side Yard in a similar way, so they must be extra mindful of these developers, where they are putting their structures, and making sure they keep them honest regarding their policies. A bunch of new development is fine, but if building something over a rail yard results in ruining the yard underneath in the process, perhaps we should pause and think for a few moments before rushing to sign any agreements.


How many 10 car trains do they operate to Brooklyn ?
ReplyDeleteThey will not be able to use VD yard. They will have to either leave it in the station, or take back east.
They could probably just board up VD and save everyone the trouble. With the LIRR's mentality twoards non-Manhattan travellers being what it is (and going the direction it's going), service has deminished to a point where they could probably get along without it.
ReplyDeleteWith 8 car limits and ESA coming, they are thinking in terms of Atlantic Avenue Shuttles, and several train sets would spend the mid-day there.
ReplyDeleteWould the west portal part of this project do anything for the passengers? Expand capacity? Shorten headways? Increase time the train is on the platform before departure? Or would this strictly help deadhead operations?
ReplyDeleteIn theory, capacity would be expanded since making a reverse move on the main ties up track space that other passenger trains could use.