Work on this past weekend's replacement of the Cherry Lane Bridge in Carle Place (part of the Main Line Grade Crossing Elimination project), coupled with signal trouble near Jamaica, threw a major wrench into rush hour service Monday morning, causing delays of 30-60 minutes across much of the system.

Photo of the new Cherry Lane Bridge ready to be moved into place
(Photo: MTA Long Island Rail Road)
The installation of the bridge and all associated track and signal work was supposed to wrap up by around 2:00a Monday morning, giving LIRR enough time to get everything in position to run a normal Monday morning rush hour. But that didn't quite happen, and the tracks were not returned to service on schedule. The first few late night trains originally expected to operate through the area were significantly delayed (if they made it to their destinations at all), and the railroad was apparently not able to finish the related track and signal work in time for the morning rush hour, so while trains were able to operate across the new bridge, they had to do so at a slower speed (30 mi/hr).

I personally do not think a late clearing outage once in a while is the end of the world—even the best planned construction work can have unforeseen issues—and when you are dealing with tight weekend outages, there can be little room for error.  It should be a stern reminder to LIRR officials, though, that people who work in glass railroad offices should not throw stones.  This was the first major blemish for the third track project, which, until this weekend, had been going remarkably smooth.

But the disruption caused by the late running outage was made avoidably worse when signal trouble west of Jamaica compounded congestion and delays, which eventually spread systemwide and reached 30 to 60 minutes, or more, in duration.  There was also signal trouble near Brooklyn-Atlantic Terminal early on in the rush hour, though that was resolved before things really became messy.

Monday morning was the first major LIRR rush hour meltdown we've seen in a while.  And while these characteristic meltdowns, thankfully, have become much less frequent in recent months, Monday's incidents (along with the Speonk Memorial Day weekend derailment) highlighted again that while we have seen nominal improvements in OTP in recent months, the railroad still has a great distance to go to bring its communication and handling of these disruptions up to where it needs to be.

The LIRR was not exactly upfront with riders about the likelihood of delays Sunday evening leading into Monday morning. Sunday afternoon, the LIRR's alerts about the project started to become very general ("Replacement of the Cherry Lane Bridge will conclude Monday morning"), and the lack of specificity about just when the work will be done, and what (if any) impacts there would be to the morning rush hour was a source of great consternation among many riders who have seen this show before. While the LIRR said that "A speed restriction will likely be in effect through Carle Place for the Monday morning commute" around 10:25p Sunday night, the railroad did not quantify any potential delays until after 4:00a Monday morning, when riders were told to expect 10-15 minute delays and some cancellations. That quickly proved to be a big underestimation of the actual extent of the delays, with late trains pushing into the 30-45 minute range (with many cancellations) not too far into the rush hour. The absence of accurate delay estimations has been a longstanding issue, and it causes great frustration among riders who go out of their way and take earlier trains to get to their destinations, yet still get to work or school late because the delay estimate was totally off.

Monday's service disruptions highlighted the persistence of many longstanding communication issues, including passengers being given conflicting or incorrect information...

Not communicating service changes (particularly cancellations) in a timely manner so people could make alternative arrangements...

The LIRR's website/TrainTime/MYmta/myLIRR applications showing riders information that's inconsistent or incorrect...

Lack of substantive announcements (or in some cases, any announcements) from train crews...

I have always said that things like communication and effective disruption handling are secondary issues...if there were never any delays and 100% of trains ran on-time, there wouldn't be any delays to mitigate, or service changes to communicate to passengers...but since the LIRR is still many miles away from that point, these persistent issues with communication and disruption mitigation—which are entirely within LIRR's control—continue to make the overall impact to passengers unnecessarily worse.  In the eyes of most riders, the railroad's nominal improvement in OTP in recent months is more than canceled out by situations like this, where some trackwork runs later than scheduled, a person or car winds up on the tracks, or it rains a little too much and the entire system falls apart.  There is more to service quality than just OTP.