| Photo of the new Cherry Lane Bridge ready to be moved into place (Photo: MTA Long Island Rail Road) |
I personally do not think a late clearing outage once in a while is the end of the world—even the best planned construction work can have unforeseen issues—and when you are dealing with tight weekend outages, there can be little room for error. It should be a stern reminder to LIRR officials, though, that people who work in glass railroad offices should not throw stones. This was the first major blemish for the third track project, which, until this weekend, had been going remarkably smooth.
But the disruption caused by the late running outage was made avoidably worse when signal trouble west of Jamaica compounded congestion and delays, which eventually spread systemwide and reached 30 to 60 minutes, or more, in duration. There was also signal trouble near Brooklyn-Atlantic Terminal early on in the rush hour, though that was resolved before things really became messy.
Monday morning was the first major LIRR rush hour meltdown we've seen in a while. And while these characteristic meltdowns, thankfully, have become much less frequent in recent months, Monday's incidents (along with the Speonk Memorial Day weekend derailment) highlighted again that while we have seen nominal improvements in OTP in recent months, the railroad still has a great distance to go to bring its communication and handling of these disruptions up to where it needs to be.
The LIRR was not exactly upfront with riders about the likelihood of delays Sunday evening leading into Monday morning. Sunday afternoon, the LIRR's alerts about the project started to become very general ("Replacement of the Cherry Lane Bridge will conclude Monday morning"), and the lack of specificity about just when the work will be done, and what (if any) impacts there would be to the morning rush hour was a source of great consternation among many riders who have seen this show before. While the LIRR said that "A speed restriction will likely be in effect through Carle Place for the Monday morning commute" around 10:25p Sunday night, the railroad did not quantify any potential delays until after 4:00a Monday morning, when riders were told to expect 10-15 minute delays and some cancellations. That quickly proved to be a big underestimation of the actual extent of the delays, with late trains pushing into the 30-45 minute range (with many cancellations) not too far into the rush hour. The absence of accurate delay estimations has been a longstanding issue, and it causes great frustration among riders who go out of their way and take earlier trains to get to their destinations, yet still get to work or school late because the delay estimate was totally off.
@LIRR you’re saying 15-20 min delays, LIARS, more like 30-45 at least and we’re still waiting at Deer Park station. Can’t you doing anything right? You can’t even estimate how late you’re running😡— Phil Holm (@Phil_Holm) June 3, 2019
@LIRRoutrage @LIRR - Nothing like taking an earlier train for a client meeting - giving yourself 40 mins of additional travel time just in case of some issue. #switchingissue happens as you would expect and still the 40 mins at 630 am would not be enough time. THANKS #LIRR— John Walls Jr (@JWJRecruiter) June 3, 2019
Monday's service disruptions highlighted the persistence of many longstanding communication issues, including passengers being given conflicting or incorrect information...
@LIRR announcements say the 538am Syosset to Penn is held. Then another announcement says cancelled. The display says “held”. Which is it? You have people here waiting needing to know what to do and you’re sending out conflicting information.— Joe Balarezo (@JoeBalarezo) June 3, 2019
Just an FYI. The 7:18 Westbury train to Penn showed up at 7:35ish. Not a big deal on a tough morning but the board never reflected that the train would be late and said it was on time until it disappeared from the board . That communication should be better.— (((Howard Silverman))) (@hsilverm11375) June 3, 2019
Not communicating service changes (particularly cancellations) in a timely manner so people could make alternative arrangements...
Are you honestly telling me that no one in your office has the slightest idea this train would be canceled until it was suppose to leave farmingdale? I find that hard to believe— Kelly Ann (@Kelso235) June 3, 2019
The LIRR's website/TrainTime/MYmta/myLIRR applications showing riders information that's inconsistent or incorrect...
But the app wasn’t updated and I had to make different accommodations. Please make your whims uniform— Jim Wilson (@JimWilson4Prez) June 3, 2019
@LIRR why does the 6:13 Bethpage train say it left the station when it’s not even here yet?! pic.twitter.com/JzGlehfIGW— Kelly Ann (@Kelso235) June 3, 2019
Lack of substantive announcements (or in some cases, any announcements) from train crews...
@LIRR 6:27 and the 6:08 has not left Ronkonkoma yet and not one announcement on the train?— frank smith (@fsmith423) June 3, 2019
5:34 from Greenlawn due at Hunters Point at 6:37 is stopped outside of Jamaica. Over 30minute delay. Please provide insight no announcements or conductors to be found..— Billie Marie (@Billie__xxx) June 3, 2019
@lirr signs showing no trains going to Atlantic from Jamaica 🤔🤷🏼♀️ so now I am back on another train going to Penn. Announcements are few and far between. Very confusing. Is this what June is going to be? Show me what I’m paying for! #fareincreases #LIRR— Kate (@Kate4ver) June 3, 2019
I have always said that things like communication and effective disruption handling are secondary issues...if there were never any delays and 100% of trains ran on-time, there wouldn't be any delays to mitigate, or service changes to communicate to passengers...but since the LIRR is still many miles away from that point, these persistent issues with communication and disruption mitigation—which are entirely within LIRR's control—continue to make the overall impact to passengers unnecessarily worse. In the eyes of most riders, the railroad's nominal improvement in OTP in recent months is more than canceled out by situations like this, where some trackwork runs later than scheduled, a person or car winds up on the tracks, or it rains a little too much and the entire system falls apart. There is more to service quality than just OTP.