LIRR riders may have to wait a little longer to ride M-9 railcars, which are meant to replace the badly worn M-3 cars and expand the LIRR’s fleet to support additional service for East Side Access. In a report that will be presented to the MTA Board LIRR Committee Meeting (pages 52-66), MTA officials will say that Kawasaki Rail Car, the company that was awarded a $1.8 billion contract in September 2013 to furnish and deliver hundreds of M-9 cars, has submitted a five-and-a-half month delay claim. And while the railroads only say that they do not agree with the claim (they don’t say why Kawasaki submitted the claim in the first place in the meeting notes), the delay might impact how soon LIRR riders can take advantage of the new rolling stock.
The M-9 procurement has already been a rocky and troublesome one—the project got rolling 32 months late (work was originally supposed to have started in January 2011, but the contract wasn’t awarded until September 2013), and then last year, the MTA approved a change order to strengthen the B-end of the cars to make them stronger in the event of a crash. The change order was issued in response to the findings from the 2013 collision of two Metro-North trains near Bridgeport and gave Kawasaki an additional four months on the project timeline, pushing the final delivery of the base order and first option cars (which would allow for the full retirement of the M-3 fleet) into 2019.
There have been several photos of pilot cars 9000 and 9001 under development at Kawasaki’s facilities in Japan, and the cars seem to be fairly well along, but there’s been no sign of the other 12 pilot cars that are supposed to be on Long Island in January (if the MTA’s schedule is still being stuck to). I don’t know all that much about the production cycle of these railcars at Kawasaki’s facility, but I do know that for these cars to get from Japan to Long Island by January, they probably have to be on a boat around Thanksgiving, if not earlier. That doesn’t leave them all that much time to make 12 whole cars and get them ready to be shipped out. If the cars are going to be affected by a five-and-a-half month delay, that means the pilot cars probably won’t start testing on Long Island until the summer of 2017, and we won’t be able to get rid of the M3’s until well into 2019:
Milestone | Original Timeline | Latest Update | With 5.5 Mo. Delay |
Start Pilot Car Testing (14 cars) | June 2015 | January 2017 | June 2017 |
Complete Pilot Testing | December 2015 | July 2017 | December 2017 |
Start Delivery of Base Order | June 2016 | January 2018 | June 2018 |
Complete Delivery of Base Order | January 2017 | August 2018 | January 2019 |
Start delivery of 1st Option Cars (88 cars) | January 2017 | September 2018 | February 2019 |
Complete delivery of 1st Option Cars (retire M-3’s) | August 2017 | March 2019 | August 2019 |
Start delivery of ESA Option Cars (77 cars) | December 2018 | April 2020 | September 2020 |
Complete Delivery of ESA Option Cars | May 2019 | October 2020 | March 2021 |
![]() |
| The front of this M-3 is being held together by an advertisement from inside (Photo: @AirlineFlyer) |
![]() |
| Torn M-3 seats repaired using duct tape (Photo: @AirlineFlyer) |
The LIRR’s fleet priories are extremely out of whack. Metro-North’s M-3A fleet is in much better shape after MN refurbished their cars several years ago, extending their fleet’s life by about a decade. It probably would have been a better idea for the LIRR to refurbish their M-3’s then too (which could have been done for a fraction of the cost), then use part of the money allocated for the M-9’s to expand the diesel fleet (a pressing need now), since the electric fleet expansion the M-9’s will enable aren’t really needed until ESA (years away). But who cares whether or not LIRR riders are seated and comfortable?