You can read the whole story on the Times Ledger's website here. Below is a brief excerpt.
Queens Tomorrow: LIRR headed to Grand Central
"Queens commuters have long heard that the East Side Access project will revolutionize their travels, but they won’t have to wait until its debut to reap some of the benefits.
"That’s because there are some major developments on tap before the Long Island Rail Road starts rolling into its new destination more than 100 feet below Grand Central Terminal in August 2019.
"Among the $8.24 billion project’s preliminary advantages for Queens straphangers:
"More capacity to store train cars is crucial to increasing LIRR service, which is why the railroad has two plans in store for commuters who use the Port Washington branch.
- An extension of a pocket track near Great Neck will boost Port Washington line service on the Long Island Rail Road and give more travel options to Queens riders bound for Penn Station.
- An extension of the LIRR yard in Port Washington will allow the MTA to store train cars at the end of main line in Queens.
- MTA officials are looking at the possibility of adding a new station in Elmhurst.
- An upgrade at Jamaica Station will raise rush hour capacity by 40 percent for Manhattan commuters and improve service to Brooklyn.
"First, LIRR will be expanding what is known as a pocket track in Great Neck, L.I. Think of a pocket track as an dead-end exit off a highway. Trains can pull off the main tracks and sit on a parallel set of rails. At the optimum time, LIRR can then route the trains back to Manhattan.
..."By January 2018, construction should be finished on a $12.1 million extension of the LIRR yard in Port Washington so that an additional 18 cars can be stored there in another move to introduce more trains for the 43,000 riders who use the line...
..."Work is to begin this fall on a dedicated platform at Jamaica Station specifically for trains to and from Brooklyn, while the other platforms will be reserved solely for trains to Penn Station and the new Grand Central Terminal.
"First, the Atlantic Shuttle will bring increased service between Jamaica and Atlantic Terminal in downtown Brooklyn. The MTA said there will be a train every 7.5 minutes, compared with midday trains running three times an hour.
..."Passing through the yards at Jamaica is currently very complicated. Trains heading to and from a host of different destinations must all switch tracks at a very slow speed and cross in front of each other, basically creating a logjam that delays everyone.
"By separating the new route to and from Brooklyn, the LIRR can simplify the rest of the switching operations through the station.The article highlights many of the upcoming projects mentioned, and it also floats the idea of re-opening the former Elmhurst station. Now this being a Queens news agency catering primarily to Queens residents and Queens City Council members, I can't put too much trust behind that idea, but it is nice to think about.
..."The $283 million price tag for the Jamaica project includes building a pocket track in Massapequa and a mid-Suffolk rail yard. The complex undertaking is scheduled for completion in January 2018...
One thing it does go into a little bit more is the Jamaica Capacity Improvements. It basically puts forth the concept that the LIRR will be reducing Atlantic Terminal service to a mere cross-borough scoot between Atlantic Terminal in Jamaica.
In my Redrawing the Map of the LIRR, Post-ESA post a couple weeks ago I mentioned that this might be something the LIRR is looking into doing. This article puts a little more force behind this school of thought. I mean, short of the Barclays Center events, Atlantic Terminal's commuting base is fairly small. Unless you work someplace in Downtown Brooklyn, connecting to the subway across the river into downtown Manhattan usually doesn't save you any time at all (it probably takes more time). Therefore, most people would prefer to just go in through Penn Station and take the subway from there.
These are exciting times for the LIRR. Many a project are about to begin, and work on the mother of all projects (ESA) seems to be progressing nicely.
Stay tuned!
I just found this blog and I think it is really a GREAT resource for the transit minded citizen!
ReplyDeleteI read the PSAS article and loved it (really informative!); I have, for a long time wondered if those west side tracks could be utilized in such a way! With the development of the far westside, it would be great if some day there would be some stops along the way; Maybe a shuttle??
I had a question that I am sure you can answer...Would it be possible to have double-decker cars on the Port Washingtion branch? It's a line that fills up fast and think it's sorely needed!
Thank you for your work, it is appreciated!
Yes and no. Yes, DE's, DM's, and C3's can all go to Port Washington (they have been up there a handful of times on testing runs and once on a revenue run when a dual mode boarded on the wrong track at NYP). However, they are prohibited by special instruction from doing so (they can suspend the special instruction when necessary to run test trains)
DeleteWhile they would provide added capacity (an 8 car DM would have about 276 more seats than an 8 M7) the added wear and tear they would put on the tracks, particularly the Manhasset Viaduct, would be a bit much for that if it was done on a daily basis. Plus the DM's are not allowed on Track 5 at Port Washington (they only fit the clearances on tracks 2, 3, and 4).
Furthermore, there simply isn't enough dual modes and C3's to add Port Washington Branch trains. The LIRR only has 22 dual modes and that fleet is stretched pretty thin when it has to support its current dual mode service for places like Port Jeff, Oyster Bay, and Speonk (and now Montauk on Fridays), so dual mode's won't be making an appearance on the Port Washington Branch in any regular capacity anytime soon.
This and this are two photos from the DM's last visit to Port Washington in March 2010. (Photo credit: Railroad.net 9C1LT1)
~ Patrick @ The LIRR Today